Hi everyone
Have heard from my solicitor whosays the following: the necessary documents to complete are in order ie End of Works Certificate signed by architect andNew Building Declaration. The water and electricity are still on builder'ssupply. The Licence of First Occupation has been applied for at the Town Hall but has not yet been issued. The builder says he expects it in 3 weeks, but solicitor cannot be sure. This document is needed to do the water and electricity contracts. The swimming pool is ready but the rest of communal areas and blocks 10 and 11 are still not finished. The builder is contracting another company to do this and expects it ready by May 2007.
Solicitor also informed me that I could complete now but advised to wait until the LIcence of First Occupation is granted.
Has anyone else had similar news? It looks as though the end may be in sight, but we have been down this road before. I am in block 9. I am doubtful about the completion of rest of complex by May 2007, based on our experience but you never know.
Cherry