off plan coto de vera

electricity licence

Off plan
Thursday, March 21, 2013 @ 6:55 PM

El Coto

 

2004 paid a deposit suppose to complete end of December 2006.

The property was not completed in the time and also with the extra 6 months .they never made any contact with us . Trying to get my deposit back they have gone into liquidation. all the properties are complete. Saw a solicitor Looked at the paper work said I would win in court but they haven't got any money to give you . The bank has taken over the site  . The bank has paid the promotor for the rest of the outstanding balance so they have the biggest debt . Has the law changed can I go for the promotors assets 

 



Like 0




3 Comments


nigel said:
Thursday, March 21, 2013 @ 6:19 PM

Hi there

You could try this website http://belegal.com/

or try this forum ,both sites you can register for free


http://www.spanishpropertyinsight.com/forums/viewtopic.php?f=2&t=3098

or view this thread

http://www.eyeonspain.com/blogs/ley5768/9390/press-release---finca-parcs---appeal-sentence-due-march-2013.aspx

This is the Finca Parcs Action Group Hellin Spanish Property Court Case.

Good Luck


Regards

Nigel



Sandra said:
Thursday, March 21, 2013 @ 6:49 PM

Hi,
Were you given a 'Bank Guarantee' or an insurance policy number
that all 'Off Plan' developments ,by law , are obliged to provide?
This guarantee/policy is to safeguard the purchaser (you) in case the development is not completed on time or the developer becomes bankrupt.Your developer has done both.
Get another lawyer.


nigel said:
Thursday, March 21, 2013 @ 8:25 PM

Hi Stinger

Read up again on website below.Very informative.

http://www.bankguaranteesinspain.com/legal.htm