Start of a New Adventure in Spain

This is a story about first buying a property off plan. That had issues. Then found an old cortijo that we would renovate and hopefully turn into a Bed & Breakfast

Hows it going ?
Sunday, June 20, 2010

 

Work was started on phase 1 of the project which involved raising the roof, building up and over of which was once the kitchen, knocking though door ways, which was quiet a job as the thickness of the walls in these old buildings

The wooden beams replaced where the old ones were rotten as well as roof tiles. Everything that was replaced was like for like.

 

The builder had been giving me weekly updates and sending pictures regularly on the progress of the work which was good and came to the point that we could not wait for a Fri/Sat when we would receive these.

 

Since work start we have been out a few times, as the builder wanted us too,so we could to see the work and to make sure all was ok, plus as things move along you can see the shape of how things will look, the sizes of room etc. I feel this is an important time as you can make some changes, do some things abit different, as we did.

 

Although we went out in March, the morning we arrived at the house there was snow on the ground it was freezing cold, and just started to rain, there was no roof on the house, rubble everywhere, standing on the first floor suryeing the work wet, cold thinking o my god. But the builder said trying to read my thoughts, getting abit worried with the expression I must have had on my face, this is it at its worse state?

 

He was right. We went out end of May the building is taking shape, with most of the main building work on this phase complete, work will start on phase 2 which is an extension on which use to house the animals.

 

Looking forward to next stage.



Like 0        Published at 1:01 PM   Comments (0)


Another Issue
Friday, June 4, 2010

 

Had e-mail from builder to say that he had received the extension of licence from the town hall, but they have only granted as a year, instead of the 2 we had requested, this is due to the fact that the town hall are cracking down on this sort of thing.

 

 

 

 

 

 

 

 

This was done in the following weeks, he agreed to our plans and work started on 8th Feb

Booked flights for the middle of January 2010 to go over for two days to go though the plans and both our ideas so we could get it down on paper making sure that we kept most of the windows etc in the same place as these was agreed by planning and town hall. This was all done; the builder took the new plans off to the architect for he’s approval.

Had phone call from the builder to say that he had spent some time measuring the property as per the plan to have some idea what could be done, but needed us to come out to look at he’s ideas, but also I had my own ideas on what I now wanted , we needed to agree on the best way to tackle this project, but also to get this renovation started as we now have a shorter dead line to complete.

So how we have a shorter deadline than we wanted. Still these things seem to happen to us, so we need to push on.