** Sorry, we accidentally deleted the original thread from mfurukawa20 **
Hi all
I was on site yesterday and spent time talking with the security guys. They were previously informed that the work will be completed by September lastest but they believe it will be completed in August. They are not allowed to let people on site except on weekdays when the sales team are about, but I managed to get a quick unescorted look around and so I have stored some photos on the link below.
http://community.webshots.com/user/Tomjohnston61?vhost=community
Virtually all work to the exterior of the buildings are completed except the set of town houses in front of block 5 which are a long way off being ready. On the other buildings it seems its now just some tidying up. The landscaping is not completed yet but the hard landscpaing is pretty much done. The roads are not down, its still just dirt tracks. Seems all the windows are in and its not a big job to tidy up the rubble thats about. Aircons are installed in many of the flats and the units are on the balconies.
I went into a few of the townhouses by the pool and the finish seems good - big bright open rooms and though its hard to see from the photos due to dust etc close up the quality looks as good if not better than I expected. There are some external "feature" brick and wood aspcts that seem really quite poor quality, but I am hoping that these are things that will be tidied up in snagging later on - they are just a bit "rough around the edges" and maybe a clean up will sort them out.
The plumbing and wiring seem to be close to complete and some bathrooms are in - again hard to see in the dusty pictures but seems to be ok quality. No light fittings but its normal in Spain that owners take possession without lighting being fitted. No kitchens were in the town houses I saw but the security guys said many of the kitchens are in the flats now but I could not get in to see them.
I am not a developer so can only guess on these things but it doesnt feel like September is an impossible date for completion but I think it will be tight. For those fans of Ikea you might be pleased to hear that the new store by the airport, at Plaza Mayor will open mid September and so there are lots of offers from the established suppliers of the complete furnishing package - I have been to see many of them, the bottom and mid range packages are generally good value but really quite awful quality, especially on crockery, cutlery, hoovers etc . Dont buy without seeing what you are getting.
And yes Sandra, your crane is still there - its being used to bring in material for those town houses in front of block 5
Tom