If you are snagging a townhouse on phase 3 please check that the wiring for all of the lighting is present
Today we were checking a 3 bedroom property on phase 3b and found that all of the wiring for wall ligts in the lounge and all bedrooms was missing plus there should be a ceiling light in the hallway
In each room the easy check is the number of light switches compared to the number of outlets and wiring as in all rooms one switch works a socket for a standard lamp and the other switches are for wall or ceiling lights
Ceiling lights are not nromally fitted in the bedrooms
There was also some wiring hanging from an outlet by the boiler and we were advised that this was for an optional timer/thermostat for the central heating but is was a bit dangerous with bare untaped wires hanging out of the wall
We can now provide sample report for apartments and townhouses on phases 3a and 3b plus the original RODA completion guide by mailing
rodaguides@inspectahomespain.com