Just had info re phase 4, block 4 Arenal 2000 has recently sold out to cajasur bank which means that all the original contractors for the fourth phase are now being replaced by new builders, supplied by the bank. Thats where the delay of completion lies.You have two options, one is to except that it´s not going to be completed until may and re-organise the rental bookings you have. There is no compensation being offered. The other option open to you is to cancel the sale and request your 30% back which they, the bank, are offering to all buyers.
This was a response to an enquirey I made to ARENAL