Hi Paul
It depends which bloque you are in ?
If you have bought in Phase 3 The electricity is still being paid for by the developer Ros Y Falcon.
So they have not switched the lifts on yet.
This is about to change as meters are being installed and the switch is about to be flicked for want of a better word.
Apparently in phase 3 Endesa the electricity company wanted 1.4 million euro just to press a button in the electrcity box to connect electric to phase 3 and the deveoper reportedly would not pay I am led to believe so dont quote me dont want Ros Y Falcon suing me . Ha Ha but it seems now all is being resolved and phase 3 electricity is about to be connected and we will all be paying our own bills .
Sue