some information i have received from MRI, how accurate it is i dont know.
Please also see a recent update and current completion dates as below:
Phase 2, Blocks 36 to 43- structure in place- brickwork completed 90%- façade painted- glazing completed - plumbing, carpentry, electricity, tiling 90%- communal areas 10%
Phase 1, Blocks 7 to 27 completed
Phase 2, Blocks 25 to 35 almost completed. Still pending the communal areas and the cleaning up.
Phase 1 blocks 7-27 completed
Phase 2 blocks 25-35 completing soon
Both phases to be released by end of Summer 07
Neil & Margie