Hi All
I have been checking my contract and I know for a fact that I paid 3005 euros holding deposit on 16th APRIL 2004 and then I made a bank transfer for remainder on 13th MAY 2004.I also know fact that the building was under way before May 13th 2004 because I was stood on the car park at the side of road outside Amarion 111 when I visited site so for me May 13th + 3 years= May 13th 2007 + 6 Months= Nov 13th 2007 at the outside. Reading Contract it states that if this happens then builder is in default.
Under my Terms and Conditions in my Sales Agreement Section 5 reads as such:-
The SELLER (GRUPO URBASA) is hereby bound to complete the construction works of the building subject of this contract within 36 months, from the moment the construction works begin,except it is impossible due to force majeure, beyond the SELLERS(GRUPO URBASA) control,including construction industry strike. Should the construction works be delayed due to causes attributable to the SELLER(GRUPO URBASA),in more than SIX MONTHS of the foreseen execution date, the BUYER (ME) could consider this sale agreement RESCINDED.In that event,the SELLER(GRUPO URBASA) shall RETURN to the Buyer (ME) the amounts that I had paid to such date, as well as the corresponding INTERESTS, calculated on a simple ANNUAL RATE of 3.5%.
So from a personel point of view I will wait until 13th NOVEMBER 2007 before I take action .
Just as a matter of interest does anyone know the date that the builders commenced work?
harvey1