Hello Everyone,
I have just been speaking to our lawyer with regards to the completion of Balcnones de Iznalloz. The completion date according to the developer will be around summer 2008 or even before.
I know people have been told March 2008.
There is one very important thing that you need to remember I am sorry if you already know this but I feel it is important.
On your contracts you can complete you purchase as soon as the construction is finished BUT.......
before the water electric etc is connected legally the development needs to be granted its habitation licence. Without the licence the development hasn't had its safety check. Also a bank will not pass a mortgage on a development which doesn't have its habitation licence.
If you are paying your legal fess on completion please bare in mind that some lawyers will want to you to complete as soon as the development is ready. !!
The habitation licence can sometimes take as long as three months after the development is complete before it is granted.
With this even if the development completes in March 2008 it will still be the summer before the site has been check and the legal services have been connected
Kindest Regards
Ruth