An update from the H Riquelme community site regarding rail, roads, and airports:-
Sucina Riquelme Station
Working group formed to press RENFE for re-opening with local
residents and current train users helping to define correct contacts
Hacienda Riquelme, Sucina, La Tercia, Peralaja - all interested.
Requires authorisation from Murcia Region Government
We have asked Murcia Region Govt for meeting to put our case for opening.
No response yet so follow-up request sent last week
Station will be unmanned – tickets on train
Will need some work to bring up to standard
Will provide a limited service to Cartegena and Murcia
Feedback from RENFE, if opening authorised, is very positive
No timescales or available date for opening.
ROADS
"Area road plans (view on Resortalia notice-board)
San Javier – Santomera (Murcia) Autovia
Dual Carriageway from AP7 to Murcia
Follows existing MU301 road
Near to Hacienda Riquelme
An Autovia exit 2 km south of Sucina
An Autovia exit just north of Sucina (link to old HR road – new flyover/bridge works)
Expected completion 6 – 9 months in HR area
Completion of full Autovia project in 2010"
Local Projects – Close to HR
Roads running along Peraleja/HR - Work restarted
Delays due to laying Town Gas pipes for resorts
Delays due to Land Ownership disputes
Completion of underpass construction for pipes
Bank Guarantees from PW/PG for completion of build
Road running from HR to Sucina (‘old road’) - Still closed
Leads to new Autovia Sucina exit then to Sucina
Roundabouts/Flyover under construction
Likely not re-opened until Autovia exit complete
Bank Guarantees from PW completion of build
Expected completion 6 -12 months
AIRPORTS
Murcia San Javier Airport
Second runway – due to open March/April 09
Allowing for all day commercial landings
Military will use own runway
Removes 3:00 pm curfew start for commercial landings
Airlines left to alter schedules accordingly
Corvera Murcia Airport
Corvera location plan (view on Resortalia notice-board)
Construction underway in 2008
Privately owned – business & bank consortium – not AENA
First runway expected completed 2010
First Commercial flights expected 2011
But apart from that I don`t know anything.