Hi all,
havnt spoken on the message board for a while as there hasnt been much to say,just seem to be going over same old problems,,, anyway i have recieved today letter
from my Brief who has been contacted by the technician who has been in charge of
the inspection for the council before the above licence can be issued, i wont bore you with it all but main points are as follows.
1. all papers requested by the council were presented by the promotor on 16th November.
2.on 2nd November the technician has issued a report saying the licence cannot be
issued due to the fact that the Disable ramp and Garage doors do not fulfil the
current regulations.
3. the promotors have been given a period of 3 months to make good these 2
faults at which time another inspection will then take place.
They have said that the rest of the development is all ok and on completion of these
2 problems the above licence should be granted, but he did say that we should not
erxpect the licence to be granted now for at leat another 2-3 months so anyone
who was expectiong tyo complete before the new year is out of luck....perhaps those of you on site could give us update if any such work has started on the above two
issues...
sorry to be the bearer of bad news prior to christmas but hope you all have a good one anyway.......
Neil