Not received anything either.
Just returned from a week in Spain. Visited SG twice but not allowed near the properties. The roads I saw are not finished. Entrance road still not open. Pavements still not finished and street lighting non existent. Masa will not be able to release until these are all in place. Under Spanish law, these should be in place before developers start to build the houses. Looks like a fair bit still to do. Builders were still working on the bank/bar at the end of M14 which looks nowhere near finished either. Builders also working frantically on the new type houses alongside M14 and M15. That made me wonder even more about their priorities. Here's hoping they get a move on.