Latest news from Peinsa: Dont know how much of this is old news, but I didnt know they were going to do all 6 phases at once. Of course we will wait and see about the start date, we have been there before! I have also just received a copy of my bank guarantee from peinsa, they have specifically run the cover to March 2008 to coincide when they think mine will be finished (Plot 18 phase 5), so they do seem to be more confident with their dates this time.
Building work commencing Mon 5th March – Infrastructure target almost met. Town Hall have been very difficult, constantly changing the goal posts but Peinsa are expecting Licenses to be in place by then.
First 6 phases will now be built together. They expect these to take 12 months with 2 construction firms working flat out.
So completion will be March 2008.
Work has also begun on the golf course next door. This is a real step forward.