Hi Everyone,
We managed to get onto the site on Saturday 23rd Feb. There had been a lot of activity during the previous week but concentrated more on the site for the school. The infrastructure for the school is apparently also Peinsa's responsibility.
We have been told that the first phase of development should start in March and will include phases 1, 2, 3, 4 and 6. All of these will be constructed simultaneously and are due to be completed in March 2008. 5, 7 and 8 are planned to be completed between March and June 2008
Our solicitor says all licences to build have been agreed by the relevant authorities but will not be released to Peinsa until 75% of the infrastructure has been completed and approved by the council inspectors. Peinsa says this will happen next month and construction will start then. Our solicitor was also told that the completion date for the first phase of development will be March 2008.
Workmen on site on Saturday were fitting gas connections. Electricity connections and drainage systems seem to be in place.
We felt a little more reassured after seeing the site which does appear to be progressing well. Like everyone else, we will be much happier when we see some evidence of construction taking place.
We have uploaded current photos.
Best wishes,
Jan and Pete (Phase 6)
This message was last edited by jansylvester on 2/25/2007.