Hi Mr UnHappy
Yes it is a big relief for us, we have certainly learnt a lesson!
We were paid out on the grounds of breach of contract. Clause 9 of our contract said that the property had to be delivered 26 months after the construction began. The start date of the construction shown in the same Clause was 31 July 2006. At the time of our claim the delay on complettion was approaching 2 years.
According to our lawyer the case was very clear, Zurich had to pay because completion of the development is seriously overdue. I realise that unfortunately many banks/insurance companies are not honouring the guarantees, at least without a fight, but in our case the lawyer's statement proved to be correct. He did say that the fact the developer, Nadalsol, was in liquidation may cause a problem, but he had a previous case which had gone to Court and the Judge ordered Zurich to pay, so he was hopeful of the same in our case. In the event Zurich paid out without the need for any legal proceedings.
As far as I am aware the LFO has still not been issued for Medina Golf.
Good luck if you are claiming on a bank guarantee.
PennyW