Kenny,
The fact that you have no services connected or facilities on-site are not reasons for not completing on time - sorry.
Unless things have changed, completion process rules are as follows:
PW normally snag 1 or 2 days prior to completion. Once initial snagging has taken place, PW have 30 working days (6 weeks) to rectify the problems and during that time, the property should remain empty. If its not, you will have to sign a form that removes any charges against PW for damage to your contents whilst the snagging is taking place.
If you're getting a pack from Homestyle, they won't install until the snagging has been signed off which means either you agree with PW when they say all has been done, or you go over to inspect at your expense..
We used QPM for our snagging - very professional and worth the money. www.quattropropertymanagementspain.com
Ian (QPM) did not sign our property off until the third inspection. Imagine the cost if I'd gone over to inspect twice before being happy. PW would not have refunded my air fare and accommodation charges.
With respect to utilities, its the gas that is the problem as it controls the hot water and heating. We completed in Nov and ours was connected in Jan. We were told the water was on but when we got there, found we were still on builders supply. didn't mind about that though as it was free. Meter now connected and monies taken from account!!