I have just recieved an e-mail from my solicitor, which is as follows:
PROPERTY PURCHASE IN SPAIN: ARENAL DUQUESA & ARENAL GOLF
Further to our conversation with Gerens on Friday, the 6th of July 2007, we would like to update you on the latest information in relation to the purchase in Arenal Duquesa and Arenal Golf.
ARENAL GOLF:
1.- PHASE III
Although the First Occupation License has been granted, completion will not take place at the notary until the electricity supply from the builder has been cut and the electricity company has arranged the connections for the electric supply.
The forecasted date to have arranged for official electricity supply, estimated by the technical department of the developer, is the 16th of July 2007. Once this has been done completions can take place, starting with the completion of those private purchase contracts that have been signed first.
2.- PHASE IV
A) BLOCKS 1,2,3:
The building works have been finished. The First Occupation License is expected to be granted on the 15th of September 2007.
B) BLOCKS 4,5:
The First Occupation License is expected to be granted on the 1st of February 2008.
C) BLOCKS 6,7,8,9:
The First Occupation License is expected to be granted on the 15th of Jun 2008.
D) BLOCKS 10,11:
The First Occupation License is expected to be granted on the 15th of April 2008.